Project Description:
WELLESLEY- RESURFACING ON ROUTE 9, FROM LIMIT OF ADD-A-LANE TO EAST OF OVERBROOK INTERSECTION
Project will include the resurfacing of the ROute 9 roadway surface only using NHS funding. THe project had initially been initiated as a larger roadway reconstruction job but the resurfacing portion will advance
Location:
  • Town of Wellesley
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Eric Mistretta
    Construction Bid Price: $6,949,951.00
    District: District 6

    Contracts (1) Progress
    # 96794 -- Construction Contract
    Resurfacing and Related Work (Including Signals) along a Section of Route 9 (Worcester Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/10/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/18/2015
    Project Initiation Form PIF Entered 03/18/2015
    Project Initiation Form PRC Submitted 03/18/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Status Advertised 08/06/2016
    Project Management
    100% Design 100% Package Received 06/30/2016
    75% Design 75% Package Received 01/14/2016
    75% Design 75% Package Comments to DE 02/25/2016
    Final Design PS&E Received 06/30/2016
    Final Design PS&E to FAPRO 08/01/2016