Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
METHUEN- HAVERHILL- MERRIMAC- AMESBURY- TRAFFIC & GUIDE SIGN REPLACEMENT ON A SECTION OF I-495
This project will consist of replacing existing guide and traffic signs, and support structures, along Interstate 495 between Route 213 (Exit 47) in Methuen and Route 150 (Exit 54) in Amesbury, including applicable signing on secondary roadways. The purpose of this project is to improve driver safety by replacing signs and supports nearing the end of their servicable life with new signs and supports meeting current retroreflectivity and design standards.
Location:
  • Town of Amesbury
  • City of Haverhill
  • Town of Merrimac
  • Town of Methuen
  • Construction Begins: Winter 2017/2018
    Resident Engineer: Mark Spinale
    Construction Bid Price: $2,419,530.75
    District: District 4

    Contracts (1) Progress
    # 101887 -- Construction Contract
    Fabrication, Installation and Removal of Overhead and Ground Mounted Guide Signs along a Section Interstate 495. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/05/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/08/2015
    Project Initiation Form PIF Entered 06/11/2015
    Project Initiation Form PRC Submitted 06/11/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 08/12/2017
    Project Management
    100% Design 100% Package Received 02/21/2017
    100% Design 100% Package Comments to DE 04/12/2017
    100% Design 100% Plans Approved 04/04/2017
    25% Design 25% Package Received 10/23/2015
    25% Design 25% Package Comments to DE 06/28/2016
    25% Design 25% Package Approved 06/28/2016
    Final Design PS&E Received 05/15/2017
    Final Design PS&E to FAPRO 07/27/2017
    Consultant Contract Process Scope to DE 04/10/2015
    Consultant Contract Process NTP Issued 06/10/2015
    Consultant Contract Process Workhours Approved 06/10/2015