Project Description:
GARDNER- LEOMINSTER- STERLING- INTERSECTION IMPROVEMENTS AT 3 LOCATIONS
The proposed work involves safety improvements at three locations: in Gardner at the Route 2 at Route 68 ramp system, in Leominster at the intersection of the Leominster Connector and Nashua Street, and in Sterling at the intersection of Route 12 and Pratt Junction Road and North Row Road. Improvements involve potential flashing beacon installation, upgrades to signage, and pavement markings.
Location:
  • City of Gardner
  • City of Leominster
  • Town of Sterling
  • Construction Begins: Spring 2019
    Resident Engineer: Carmen Ramirez
    Construction Bid Price: $1,853,425.50
    District: District 3
    Current Status: Contractor has tested equipment and awaiting the start of O & M pending results of 30 day burn-in period which will begin once the final site (295SB-CCTV-1.9)is operational. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 03/18/2024)

    Contracts (3) Progress
    # 105766 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at 3 Locations Completed
    # 77884 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86790 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/21/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor has tested equipment and awaiting the start of O & M pending results of 30 day burn-in period which will begin once the final site (295SB-CCTV-1.9)is operational. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/08/2015
    Project Initiation Form PIF Entered 04/08/2015
    Project Initiation Form PRC Submitted 04/14/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 09/01/2018
    Project Management
    100% Design 100% Package Received 03/09/2018
    100% Design 100% Package Comments to DE 04/18/2018
    25% Design 25% Package Received 07/28/2017
    25% Design 25% Package Comments to DE 09/25/2017
    25% Design Design Public Hearing 11/08/2017
    75% Design 75% Package Received 12/29/2017
    75% Design 75% Package Comments to DE 02/06/2018
    Final Design PS&E Received 05/15/2018
    Final Design PS&E to Peer Reviewer 05/29/2018
    Final Design PS&E to FAPRO 08/20/2018