Project Description:
FITCHBURG- BRIDGE REPLACEMENT AND RELATED WORK, F-04-017, WATER STREET (STATE 2A) OVER BOULDER DRIVE AND PANAM RAILROAD & F-04-018, WATER STREET (ROUTE 12) OVER NORTH NASHUA RIVER
F-04-018 was originally constructed in 1937 and consists of built-up plate girders with vertical stiffeners and rivited connections. The abutments are gravity on spread footings and are integral with the channel wall system. The deck was rebulit in 1961. The overall condition is fair to poor with Items 58,59,& 60 5-5-4 repectively.
Location:
  • City of Fitchburg
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2024/2025
    Project Manager: Jacob Tanoglu
    Estimated Total Contract Cost: $29,171,230.55
    Estimated Total Federal Participating Construction Cost: $31,394,728.07
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: 100% Package Received (as of 12/04/2023 )

    Contracts (2) Progress
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86790 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: FITCHBURG
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • HIP-BR
  • Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $15,068,822.40
    State Cost: $3,767,205.60
    Total Cost: $18,836,028.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/09/2015
    Project Initiation Form PIF Entered 04/09/2015
    Project Initiation Form PIF Entered 07/19/2016
    Project Initiation Form PRC Submitted 04/09/2015
    Project Review Committee PRC Approved 03/23/2017
    Project Review Committee Resubmitted 03/20/2017
    Project Management
    100% Design 100% Package Received 12/04/2023
    25% Design 25% Package Received 04/06/2020
    25% Design 25% Package Comments to DE 07/06/2020
    25% Design 25% Package Received - Resub 1 04/13/2021
    25% Design Design Public Hearing 12/15/2022
    75% Design 75% Package Received 04/10/2023
    75% Design 75% Package Received 05/02/2023
    75% Design 75% Package Comments to DE 06/21/2023