Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BROOKFIELD- EAST BROOKFIELD- BRIDGE REPLACEMENT, B-26-006 = E-02-001, SOUTH POND ROAD OVER SOUTH POND INLET
The existing structure was built in 1956 and also includes a water control structure that was attached to the bridge post construction. The water control system needs to be upgraded. The overall condition is poor (6-4-4).
Location:
  • Town of East Brookfield
  • Construction Begins: Spring 2020
    Resident Engineer: David Windoloski
    Construction Bid Price: $2,836,005.00
    District: District 3

    Contracts (2) Progress
    # 109686 -- Construction Contract
    Bridge Replacement Br. No. B-26-006=E-02-001 (NEXT D BEAMS) South Pond Road over South Pond Inlet Completed
    # 77877 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 05/11/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/09/2015
    Project Initiation Form PIF Entered 04/09/2015
    Project Initiation Form PRC Submitted 04/09/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 09/14/2019
    Project Management
    100% Design 100% Package Received 01/10/2019
    100% Design 100% Package Comments to DE 03/04/2019
    100% Design 100% Plans Approved 03/14/2019
    100% Design 100% Plans Complete 03/14/2019
    25% Design 25% Package Received 06/16/2017
    25% Design 25% Package Comments to DE 10/24/2017
    25% Design 25% Package Approved 10/27/2017
    25% Design 25% Package Received - Resub 1 01/18/2018
    25% Design Design Public Hearing 03/22/2018
    75% Design 75% Package Received 09/12/2018
    75% Design 75% Package Comments to DE 10/16/2018
    75% Design 75% Plans Approved 11/20/2018
    75% Design 75% Plans Complete 11/20/2018
    Final Design PS&E Received 04/04/2019
    Final Design PS&E to Peer Reviewer 05/20/2019
    Final Design Peer Review Comments to DE 05/24/2019
    Final Design PS&E to FAPRO 08/30/2019