| Project Description: |
BROOKFIELD- EAST BROOKFIELD- BRIDGE REPLACEMENT, B-26-006 = E-02-001, SOUTH POND ROAD OVER SOUTH POND INLET
The existing structure was built in 1956 and also includes a water control structure that was attached to the bridge post construction. The water control system needs to be upgraded. The overall condition is poor (6-4-4).
|
| Location: |
|
| Construction Begins: | Spring 2020 |
| Resident Engineer: | David Windoloski![]() |
| Construction Bid Price: | $2,836,005.00 |
| District: | District 3 |
|