Project Description:
EASTON- CORRIDOR IMPROVEMENTS ON ROUTE 138 INCLUDING INTERSECTION IMPROVEMENTS AT ROUTE 138 (WASHINGTON STREET) AND ELM STREET
Installation of traffic signals including ped signals is proposed at this location. In addition, the realignment of the west leg of Elm Street is proposed to to align with the opposite Elm Street approach. The intersection improvements will involve reconstructing approximately 500 feet of Washington Street, 100 feet of the east leg of Elm Street, and 500 feet of the realigned west leg of Elm Street. Sidewalks will be constructed on both sides of Washington Street and on both sides of the west leg of Elm Street, connecting to an existing sidewalk west of Frothingham Drive. Bike accommodating shoulders will also be provided on Washington Street within the existing right of way.   Proposed related work includes constructing sidewalks along Washington Street Northerly both sides between Elm Street and Union Street, a distance of approximately 3,500 feet. The existing closed drainage system will also be modified within the project limits to better capture and treat stormwater runoff. Five foot bike lanes are proposed on the intersection approaches and on the Washington Street corridor between Elm Street and Union Street. Pavement rehabilitation will generally be accomplished through milling and overlay, with full depth box widening where necessary at the intersection. The realignment of Elm Street will require full depth construction.
Location:
  • Town of Easton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2025
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $7,317,939.00
    Estimated Total Federal Participating Construction Cost: $9,508,591.97
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: 100% Package Comments to DE (as of 10/10/2023 )

    Contracts (1) Progress
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: EASTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $3,200,000.00
    State Cost: $800,000.00
    Total Cost: $4,000,000.00

    Planned Federal FY: 2025
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: EASTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,406,873.60
    State Cost: $1,101,718.40
    Total Cost: $5,508,592.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/04/2015
    Project Initiation Form PIF Entered 01/28/2016
    Project Initiation Form PRC Submitted 01/28/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Management
    100% Design 100% Package Received 06/02/2023
    100% Design 100% Package Comments to DE 10/10/2023
    25% Design 25% Package Received 08/28/2018
    25% Design 25% Package Comments to DE 01/23/2019
    25% Design 25% Package Received - Resub 1 02/25/2022
    25% Design Design Public Hearing 05/12/2022
    75% Design 75% Package Received 10/07/2022
    75% Design 75% Package Comments to DE 01/17/2023