Planned Federal FY: |
2028 |
Responsible MPO: |
Cape Cod Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
DENNIS
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
AC 2027-2028; Municipality is TAP proponent; CMAQ analysis to be completed when all required inputs are available; TFPC $11,340,000; STBG - $8,946,197; TAP - $2,993,803
|
|
Category |
FA - Surface Trans. Block Grant (STBG) |
|
Federal Cost: |
$2,175,057.60 |
State Cost: |
$543,764.40 |
Total Cost: |
$2,718,822.00 |
|
|
|
Planned Federal FY: |
2029 |
Responsible MPO: |
Cape Cod Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
DENNIS
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
AC 2027-2028; Municipality is TAP proponent; CMAQ analysis to be completed when all required inputs are available; TFPC $11,340,000; STBG - $8,946,197; TAP - $2,993,803
|
|
Category |
FA - Trans. Alternative Prgm (TAP) |
|
Federal Cost: |
$2,703,100.80 |
State Cost: |
$675,775.20 |
Total Cost: |
$3,378,876.00 |
|
|
|
Planned Federal FY: |
2029 |
Responsible MPO: |
Cape Cod Metropolitan Planning Organization |
Location: |
Municipality |
Cities: |
DENNIS
|
Category: |
Advertised Projects Constr. |
Budget Section: |
1A |
Advance Construct: |
No |
Air Quality Exempt: |
No |
|
AC 2027-2028; Municipality is TAP proponent; CMAQ analysis to be completed when all required inputs are available; TFPC $11,340,000; STBG - $8,946,197; TAP - $2,993,803
|
|
Category |
FA - Surface Trans. Block Grant (STBG) |
|
Federal Cost: |
$4,529,841.60 |
State Cost: |
$1,132,460.40 |
Total Cost: |
$5,662,302.00 |
|
|
|
|