Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DENNIS- CORRIDOR AND STREETSCAPE IMPROVEMENTS ON MAIN STREET (ROUTE 28), FROM UNCLE BARNEYS ROAD TO OLD MAIN STREET (PHASE 2)
This project is the second phase of improvements on Route 28 to address a lack of adequate bicycle and pedestrian accommodation. Work on this project includes the installation of sidewalks and bike lanes along Route 28. The Route 28/School Street intersection will be evaluated for traffic signal installation. Old Main Street will be realigned at Route 28. The project also includes drainage improvements and street lighting.
Location:
  • Town of Dennis
  • Design Responsibility: Municipality
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2027
    Project Manager: David Shedd
    Estimated Total Contract Cost: $10,125,000.00
    Estimated Total Federal Participating Construction Cost: $10,500,000.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Cape Cod Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: DENNIS
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • AC 2027-2028; Municipality is TAP proponent; CMAQ analysis to be completed when all required inputs are available; TFPC $11,760,000; STBG - $9,766,198; TAP - $1,993,803
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $480,000.00
    State Cost: $120,000.00
    Total Cost: $600,000.00

    Planned Federal FY: 2027
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: DENNIS
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • AC 2027-2028; Municipality is TAP proponent; CMAQ analysis to be completed when all required inputs are available; TFPC $11,760,000; STBG - $9,766,198; TAP - $1,993,803
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $7,812,958.40
    State Cost: $1,953,239.60
    Total Cost: $9,766,198.00

    Planned Federal FY: 2028
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: DENNIS
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • AC 2027-2028; Municipality is TAP proponent; CMAQ analysis to be completed when all required inputs are available; TFPC $11,760,000; STBG - $9,766,198; TAP - $1,993,803
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $1,115,042.40
    State Cost: $278,760.60
    Total Cost: $1,393,803.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/06/2015
    Project Initiation Form PIF Entered 05/06/2015
    Project Initiation Form PRC Submitted 05/12/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Management