BOSTON- STORROW DRIVE REALIGNMENT @ MEEI/CHARLES CIRCLE INCLUDES BRIDGE REPLACEMENT, B-16-257 & B-16-258 (DESIGN)
MassDOT proposes a roadway and bridge relocation project to consolidate and realign the Storrow Drive Westbound Travel movements into the Eastbound Barrel, thus making provisions to improve bicycle, pedestrian, vehicular, and transit movements, safety and mobility at Charles Circle on Cambridge Street in Boston. The scope will include replacement of the existing bridges serving on-ramp and off-ramp vehicular movements to and from Charles Circle and Storrow Drive to accommodate the expansion of Mass Eye and Ear Infirmary MEEI, including pedestrian and bicyclist movements between MBTA Red-Line Rapid Transit Station and Charles River Esplanade.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Michael O'Dowd
    Estimated Total Contract Cost: $97,750,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 115773 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/08/2015
    Project Initiation Form PIF Entered 05/08/2015
    Project Initiation Form PRC Submitted 05/08/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Management