Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MILFORD- HOPKINTON- WESTBOROUGH- SOUTHBOROUGH- MARLBORO- HUDSON- BERLIN- PAVEMENT PRESERVATION AND RELATED WORK ON I-495
The Interstate Maintenance Resurfacing will improve the pavement condition and make safety improvements.
Location:
  • Town of Berlin
  • Town of Hopkinton
  • Town of Hudson
  • City of Marlborough
  • Town of Milford
  • Town of Southborough
  • Town of Westborough
  • Construction Begins: Spring 2022
    Resident Engineer: Steven Crain
    Construction Bid Price: $18,647,736.11
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the STATEWIDE.
    District: District 3

    Contracts (1) Progress
    # 117410 -- Construction Contract
    Resurfacing and Related Work along Sections of Interstate 495 5% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 05/06/2022
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: BERLIN
    HOPKINTON
    HUDSON
    MARLBOROUGH
    MILFORD
    SOUTHBOROUGH
    WESTBOROUGH
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - Interstate Maintenance
    Federal Cost: $20,438,910.00
    State Cost: $2,270,990.00
    Total Cost: $22,709,900.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 05/27/2015
    Project Initiation Form PRC Submitted 05/27/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 02/19/2022
    Project Management
    100% Design 100% Package Received 01/13/2022
    25% Design 25% Package Received 11/15/2021
    75% Design 75% Package Received 11/15/2021
    75% Design 75% Package Comments to DE 12/07/2021
    Final Design PS&E Received 01/13/2022
    Final Design PS&E to FAPRO 02/07/2022