ATTLEBORO TO NORWOOD- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF I-95
This project will replace the guide and traffic signs, and supports, on Interstate 95 between the Rhode Island/Massachusetts state line in Attleboro and Neponset Street (Exit 11) in Norwood, including applicable signs on intersecting secondary roads. To insure driver safety, new signs and supports will meet current retroreflectivity and design standards.
Location:
  • City of Attleboro
  • Town of Norwood
  • Construction Begins: Spring 2019
    Resident Engineer: Charles Young
    Construction Bid Price: $6,238,931.37
    District: District 5

    Contracts (1) Progress
    # 105997 -- Construction Contract
    Fabrication, Installation and Removal of Overhead and Ground Mounted Guide Signs (Including 3 Variable Message Signs (VMS) and a Closed Circuit Television Camera (CCTV)) along Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/01/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 06/11/2015
    Project Initiation Form PRC Submitted 06/11/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 09/22/2018
    Project Management
    100% Design 100% Package Received 04/17/2018
    100% Design 100% Package Comments to DE 05/31/2018
    100% Design 100% Plans Approved 05/25/2018
    25% Design 25% Package Received 08/09/2017
    25% Design 25% Package Comments to DE 09/15/2017
    25% Design 25% Package Approved 09/14/2017
    75% Design 75% Package Received 04/17/2018
    Final Design PS&E Received 08/08/2018
    Final Design PS&E to FAPRO 09/07/2018
    Consultant Contract Process Scope to DE 02/21/2017
    Consultant Contract Process NTP Issued 05/10/2017
    Consultant Contract Process Workhours Approved 05/05/2017