Project Description:
READING TO LYNNFIELD- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF I-95 (SR 128)
This project consists of replacing guide and traffic signs, and supports, on Interstate Route 95 (Route 128) between Route 28 (Exit 38) in Reading and US Route 1 (Exit 44) in Lynnfield, including applicable signs on intersecting secondary roads. To insure driver safety, new signs and supports will meet curretn retroreflectivity and design standards.
Location:
  • Town of Lynnfield
  • Town of Reading
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Anthony Neve
    Construction Bid Price: $3,637,873.00
    District: District 4

    Contracts (1) Progress
    # 109689 -- Construction Contract
    Fabrication and Installation of Overhead and Ground Mounted Guide and Traffic Signs on a Section of Interstate 95 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/26/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 06/11/2015
    Project Initiation Form PRC Submitted 06/11/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 09/14/2019
    Project Management
    100% Design 100% Package Received 05/13/2019
    100% Design 100% Package Comments to DE 06/17/2019
    100% Design 100% Plans Approved 06/14/2019
    25% Design 25% Package Received 01/11/2018
    75% Design 75% Package Received 05/13/2019
    Final Design PS&E Received 08/08/2019
    Final Design PS&E to FAPRO 08/30/2019
    Consultant Contract Process Scope to DE 08/08/2017
    Consultant Contract Process NTP Issued 08/18/2017
    Consultant Contract Process Workhours Approved 08/17/2017