Project Description:
CHELSEA TO DANVERS- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF US ROUTE 1
The project will consist of replacing guide and traffic signs, and supports, on US Route 1 between the Tobin Bridge in Chelsea and Interstate 95 at the Danvers/Topsfield line, including applicable signing on intersecting secondary roads. To insure continued driver safety, new signs and supports meeting current retroreflectivity and design standards will be provided
Location:
  • City of Chelsea
  • Town of Danvers
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Mark Spinale
    Construction Bid Price: $5,584,562.00
    District: District 4
    Current Status: The contractor is chipping out old foundations and installing new fence at the old OD in the median during the daytime. The removal of old signs and sign structures continues. (as of 12/26/2023)

    Contracts (1) Progress
    # 109465 -- Construction Contract
    Fabrication and Installation of Overhead and Ground Mounted Guide and Traffic Signs along a Section of Route 1

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/30/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor is chipping out old foundations and installing new fence at the old OD in the median during the daytime. The removal of old signs and sign structures continues.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 06/11/2015
    Project Initiation Form PRC Submitted 06/11/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 08/24/2019
    Project Management
    100% Design 100% Package Received 07/16/2018
    100% Design 100% Package Comments to DE 07/24/2019
    100% Design 100% Plans Approved 07/23/2019
    25% Design 25% Package Received 10/13/2017
    25% Design 25% Package Comments to DE 01/12/2018
    25% Design 25% Package Approved 01/12/2018
    75% Design 75% Package Received 07/16/2018
    Final Design PS&E Received 06/04/2019
    Final Design PS&E to FAPRO 08/13/2019
    Consultant Contract Process Scope to DE 06/22/2016
    Consultant Contract Process NTP Issued 08/19/2016
    Consultant Contract Process Workhours Approved 08/17/2016