Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LONGMEADOW- SPRINGFIELD- INTERSTATE MAINTENANCE & RELATED WORK ON I-91
The purpose of this resurfacing project is to preserve the pavement and provide highway safety improvements. The project will also include repairs to S-24-054 carrying I-91 over Main Street, S-24-056 carrying I-91 over Broad Street and L-14-001 carrying I-91 over Emerson Road.
Location:
  • Town of Longmeadow
  • City of Springfield
  • Construction Begins: Autumn 2016
    Resident Engineer: Michael Los
    Construction Bid Price: $9,474,759.24
    District: District 2

    Contracts (2) Progress
    # 77854 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 95848 -- Construction Contract
    Resurfacing and Related Work (Including 3 Bridges) along 2 Sections of Interstate 91. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/20/2016
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 05/27/2015
    Project Initiation Form PRC Submitted 05/27/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 07/16/2016
    Project Management
    100% Design 100% Package Received 01/28/2016
    100% Design 100% Package Comments to DE 03/28/2016
    25% Design 25% Package Received 11/10/2015
    75% Design 75% Package Received 11/10/2015
    75% Design 75% Package Comments to DE 12/28/2015
    Final Design PS&E Received 04/05/2016
    Final Design PS&E Received 04/27/2016
    Final Design PS&E to Peer Reviewer 04/07/2016
    Final Design PS&E to Peer Reviewer 04/28/2016
    Final Design Peer Review Comments to DE 04/21/2016
    Final Design PS&E to FAPRO 07/01/2016