Project Description:
QUINCY- MILTON- BOSTON- INTERSTATE MAINTENANCE & RELATED WORK ON I-93
I-93 SE Expressway Interstate Maintenance Resurfacing is proposed with a preservation treatment or thin bonded overlay to extend the pavement's service life and improve safety.
Location:
  • City of Boston
  • Town of Milton
  • City of Quincy
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2023
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $36,619,595.15
    Estimated Total Federal Participating Construction Cost: $37,710,926.98
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 06/24/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    MILTON
    QUINCY
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Decrease from$31,771,350.00 to $18,517,908 via STIP Action 6.
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - Interstate Maintenance
    Federal Cost: $16,666,117.20
    State Cost: $1,851,790.80
    Total Cost: $18,517,908.00

    Planned Federal FY: 2023
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    MILTON
    QUINCY
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Increase from $6,900,000.00 to $19,074,016 via STIP Action 6.
  • Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $15,259,212.80
    State Cost: $3,814,803.20
    Total Cost: $19,074,016.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 05/27/2015
    Project Initiation Form PRC Submitted 05/27/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 06/24/2023
    Project Management
    100% Design 100% Package Received 02/07/2023
    100% Design 100% Package Comments to DE 03/15/2023
    25% Design 25% Package Received 11/28/2022
    75% Design 75% Package Received 11/28/2022
    75% Design 75% Package Comments to DE 01/09/2023
    Final Design PS&E Received 04/11/2023
    Final Design PS&E to FAPRO 06/12/2023