Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LITTLETON- WESTFORD- INTERSTATE MAINTENANCE AND RELATED WORK ON I-495
I-495 Interstate Maintenance Resurfacing will restore exisitng surface with new friction course and safety improvements.
Location:
  • Town of Littleton
  • Town of Westford
  • Construction Begins: Winter 2018/2019
    Resident Engineer: John Bowes
    Construction Bid Price: $15,398,688.83
    District: District 3

    Contracts (1) Progress
    # 104116 -- Construction Contract
    Resurfacing and Related Work (Including 5 Bridges) along Sections of Interstate 495 (Blue Star Memorial Highway) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/09/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 05/28/2015
    Project Initiation Form PRC Submitted 05/28/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 06/02/2018
    Project Management
    100% Design 100% Package Received 05/02/2018
    100% Design 100% Package Received 05/02/2018
    25% Design 25% Package Received 02/21/2018
    25% Design 25% Package Comments to DE 03/26/2018
    75% Design 75% Package Received 02/21/2018
    75% Design 75% Package Comments to DE 03/26/2018
    Final Design PS&E Received 05/02/2018
    Final Design PS&E to FAPRO 05/21/2018