Project Description:
FOXBOROUGH- PLAINVILLE- WRENTHAM- FRANKLIN- INTERSTATE MAINTENANCE & RELATED WORK ON I-495 NORTHBOUND
Location:
  • Town of Foxborough
  • Town of Plainville
  • Town of Wrentham
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Charles Young
    Construction Bid Price: $5,435,751.50
    District: District 5
    Current Status: Current Operations: The contractor is prepping a plan to address remedial work on bridge joints Future Operations: Bridge joint remedial work. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 05/14/2025)

    Contracts (1) Progress
    # 113596 -- Construction Contract
    Resurfacing and Related Work (Including 5 Bridges) along a Section of Interstate 495N Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/26/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Current Operations: The contractor is prepping a plan to address remedial work on bridge joints Future Operations: Bridge joint remedial work. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 05/28/2015
    Project Initiation Form PRC Submitted 05/28/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 12/05/2020
    Project Management
    100% Design 100% Package Received 10/02/2020
    25% Design 25% Package Received 07/08/2020
    75% Design 75% Package Received 07/08/2020
    75% Design 75% Package Comments to DE 08/31/2020
    Final Design PS&E Received 10/02/2020
    Final Design PS&E to FAPRO 11/23/2020