CHICOPEE- SPRINGFIELD- INTERSTATE MAINTENANCE & RELATED WORK ON I-291
The work to be done under this contract consists of roadway pavement preservation and related work on a section of Interstate 291 (Eastbound and Westbound) in the City of Springfield and the City of Chicopee. The project begins in Springfield at MM 0.56 (northerly limit of Viaduct Project), and extends northeasterly into Chicopee ending at MM 5.1 (southern limit of the Robinson Bridge). The length of the project is 4.54 miles.
Location:
  • City of Chicopee
  • City of Springfield
  • Construction Begins: Summer 2017
    Resident Engineer: Todd Moylan
    Construction Bid Price: $3,328,447.50
    District: District 2

    Contracts (1) Progress
    # 99399 -- Construction Contract
    Resurfacing and Related Work along a Section of Interstate 291 (Springfield Expressway). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/25/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 05/28/2015
    Project Initiation Form PRC Submitted 05/28/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 12/31/2016
    Project Management
    100% Design 100% Package Received 12/14/2016
    100% Design 100% Package Comments to DE 12/15/2016
    25% Design 25% Package Received 08/23/2016
    25% Design 25% Package Comments to DE 10/04/2016
    75% Design 75% Package Received 08/23/2016
    75% Design 75% Package Comments to DE 10/04/2016
    Final Design PS&E Received 12/14/2016
    Final Design PS&E to FAPRO 12/19/2016