Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MARLBOROUGH- SUDBURY- STORMWATER IMPROVEMENTS ALONG ROUTE 20
Stormwater improvement along Route 20 to treat discharges to Gristmill Pond and Unnamed Tributary
Location:
  • City of Marlborough
  • Town of Sudbury
  • Construction Begins: Winter 2017/2018
    Resident Engineer: Alan Webb
    Construction Bid Price: $119,019.00
    District: District 3

    Contracts (1) Progress
    # 100934 -- Construction Contract
    Stormwater Drainage Improvements and Related Work along a Section of Route 20 (Boston Post Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/25/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 11/10/2015
    Project Initiation Form PRC Submitted 11/10/2015
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 07/01/2017
    Project Management
    100% Design 100% Package Received 02/01/2017
    100% Design 100% Package Comments to DE 03/08/2017
    75% Design 75% Package Received 10/06/2016
    Final Design PS&E Received 04/24/2017
    Final Design Peer Review Comments to DE 05/16/2017
    Final Design PS&E to FAPRO 06/16/2017