Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOURNE- WAREHAM- RESURFACING AND RELATED WORK ON ROUTE 25
The proposed NHS Pavement Preservation will resurface the pavement and improve safety.
Location:
  • Town of Bourne
  • Town of Wareham
  • Construction Begins: Autumn 2019
    Resident Engineer: Dylan Hipolito
    Construction Bid Price: $8,552,099.13
    District: District 5

    Contracts (1) Progress
    # 108459 -- Construction Contract
    Resurfacing and Related Work (Including 6 Bridges) along Sections of Route 25 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/04/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 05/27/2015
    Project Initiation Form PRC Submitted 05/27/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 06/29/2019
    Project Management
    100% Design 100% Package Received 04/25/2019
    25% Design 25% Package Received 02/05/2019
    25% Design 25% Package Comments to DE 03/08/2019
    75% Design 75% Package Received 02/05/2019
    75% Design 75% Package Comments to DE 03/08/2019
    Final Design PS&E Received 04/25/2019
    Final Design PS&E to FAPRO 06/18/2019
    Final Design PS&E Received - Resub 1 05/30/2019