Project Description:
FALL RIVER- RESURFACING AND RELATED WORK ON ROUTE 24
The NHS Pavement Preservation project proposes resurfacing to extend pavement service and safety.
Location:
  • City of Fall River
  • Construction Begins: Autumn 2019
    Resident Engineer: Alfredo Nunez
    Construction Bid Price: $11,288,671.50
    District: District 5

    Contracts (1) Progress
    # 108466 -- Construction Contract
    Resurfacing and Related Work (Including 9 Bridges) along a Section of Route 24 (Fall River Expressway) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/04/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/15/2015
    Project Initiation Form PIF Entered 05/27/2015
    Project Initiation Form PRC Submitted 05/27/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 06/29/2019
    Project Management
    100% Design 100% Package Received 03/29/2019
    100% Design 100% Package Comments to DE 04/29/2019
    25% Design 25% Package Received 04/27/2017
    25% Design 25% Package Comments to DE 07/12/2017
    75% Design 75% Package Received 04/27/2017
    75% Design 75% Package Comments to DE 07/12/2017
    75% Design 75% Package Received - Resub 1 03/14/2019
    Final Design PS&E Received 06/10/2019
    Final Design PS&E to FAPRO 06/17/2019