Project Description:
FRAMINGHAM- RECONSTRUCTION OF UNION AVENUE, FROM PROCTOR STREET TO MAIN STREET
The project involves improvements to Union Ave from Proctor Street to Main Street, with limited work on intersecting local roadways. Specifically, the proposed improvements include full depth pavement reconstruction, sidewalk reconstruction, traffic signal improvements, streetscape improvements, bicycle accommodation, warning and regulatory signing and pavement markings. The existing traffic signal at Mt. Wayte Avenue will be reconstructed and new traffic signals will be constructed at the Union Ave intersections with Lincoln Street and Walnut Street. Streetscape and ornamental lighting improvements will be constructed from the southerly beginning of the project up to the intersection with Lincoln Street. Minor roadway widening of less than 2 feet is proposed between Proctor St and Lexington St in order to provide a sufficient cross section for travel lanes, bike lanes and on-street parking. The Town is constructing significant stormwater improvements as part of a separate utility project to be completed prior to the roadway improvements.
Location:
  • Town of Framingham
  • Construction Begins: Autumn 2021
    Resident Engineer: Adam Cline
    Construction Bid Price: $11,340,877.00
    District: District 3

    Contracts (1) Progress
    # 114723 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals and Alterations to Br. No. F-07-004) on a Section of Union Avenue Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/06/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/28/2015
    Project Initiation Form PIF Entered 05/28/2015
    Project Initiation Form PRC Submitted 06/08/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 06/05/2021
    Project Management
    100% Design 100% Package Received 09/08/2020
    100% Design 100% Package Comments to DE 10/30/2020
    25% Design 25% Package Received 09/15/2015
    25% Design 25% Package Comments to DE 02/04/2016
    25% Design Design Public Hearing 10/26/2017
    75% Design 75% Package Received 02/27/2020
    75% Design 75% Package Comments to DE 05/11/2020
    Final Design PS&E Received 02/05/2021
    Final Design PS&E Received - Resub 1 03/25/2021