Project Description:
ACTON- INTERSECTION & SIGNAL IMPROVEMENTS AT KELLEY'S CORNER, ROUTE 111 (MASSACHUSETTS AVENUE) AND ROUTE 27 (MAIN STREET)
The project involves roadway rehabilitation to approximately 0.4 miles on Main Street (Rte. 27) and approximately .6 miles on Massachusetts Avenue (Rte. 111). Additional roadway work includes providing pedestrian and bicycle accommodations on both sides of all roadways, curb cut management and the inclusion of center turn lanes. The proposed improvements also include new signals at the intersection of Route 27 and Route 111 and potential signalization at Route 27 and Community Lane. Additional streetscape and utility improvements including landscaping, and street lighting will also be considered.
Location:
  • Town of Acton
  • Construction Begins: Summer 2022
    Resident Engineer: Patrick Marion
    Construction Bid Price: $18,577,540.50
    District: District 3

    Contracts (2) Progress
    # 118477 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Kelley’s Corner, Route 111 (Massachusetts Avenue) at Route 27 (Main Street) 47% Complete
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/01/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/28/2015
    Project Initiation Form PIF Entered 05/28/2015
    Project Initiation Form PIF Entered 11/25/2015
    Project Initiation Form PIF Entered 11/25/2015
    Project Initiation Form PRC Submitted 06/08/2015
    Project Initiation Form PRC Submitted 11/25/2015
    Project Review Committee PRC Tabled 06/25/2015
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 06/04/2022
    Project Management
    100% Design 100% Package Received 10/29/2020
    100% Design 100% Package Comments to DE 01/06/2021
    25% Design 25% Package Received 02/05/2018
    25% Design 25% Package Comments to DE 06/13/2018
    25% Design Design Public Hearing 03/05/2019
    75% Design 75% Package Received 12/09/2019
    75% Design 75% Package Comments to DE 03/11/2020
    Final Design PS&E Received 11/18/2021
    Final Design PS&E to FAPRO 05/17/2022
    Final Design PS&E Received - Resub 1 03/09/2022
    Final Design PS&E Received - Resub 2 04/11/2022