Project Description:
REHOBOTH- INTERSECTION IMPROVEMENTS & RELATED WORK AT WINTHROP STREET (ROUTE 44) AND ANAWAN STREET (ROUTE 118)
Work on this project consists of improvements at the intersection of Route 44 and Route 118. This intersection has been identified as a high crash location within the Southeast Massachusetts Region. Improvements multi-modal accommodation will be included.
Location:
  • Town of Rehoboth
  • Construction Begins: Winter 2022/2023
    Resident Engineer: Erik Trowbridge
    Construction Bid Price: $4,244,836.00
    District: District 5
    Current Status: The Contractor has ceased work operations for the Winter and tentatively plans to remobilize within the next few weeks. Verizon is on site relocating cables to new utility poles. This work is expected to continue over the next several weeks. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 04/01/2024)

    Contracts (2) Progress
    # 120706 -- Construction Contract
    Intersection Improvements and Related Work (Including Roundabout Construction) Winthrop Street (Route 44) at Bay State Road/Anawan Street (Route 118) 43% Complete
    # 77851 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/09/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The Contractor has ceased work operations for the Winter and tentatively plans to remobilize within the next few weeks. Verizon is on site relocating cables to new utility poles. This work is expected to continue over the next several weeks. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2015
    Project Initiation Form PIF Entered 06/09/2015
    Project Initiation Form PRC Submitted 06/16/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 11/05/2022
    Project Management
    100% Design 100% Package Received 12/18/2020
    100% Design 100% Package Comments to DE 02/18/2021
    25% Design 25% Package Received 05/20/2019
    25% Design 25% Package Comments to DE 08/19/2019
    25% Design Design Public Hearing 01/28/2020
    75% Design 75% Package Received 04/15/2020
    75% Design 75% Package Comments to DE 07/13/2020
    75% Design 75% Plans Complete 08/12/2020
    Final Design PS&E Received 07/20/2021
    Final Design PS&E Received - Resub 1 11/17/2021