WEYMOUTH- RECONSTRUCTION ON ROUTE 3A, INCLUDING PEDESTRIAN AND TRAFFIC SIGNAL IMPROVEMENTS
THe intent of this project is to reconstruct Route 3A and address poor traffic operations along the corridor. The project will also upgrade accomodations for bicyclists and pedestrians.
Location:
  • Town of Weymouth
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $10,311,400.00
    Estimated Total Federal Participating Construction Cost: $10,780,100.00
    District: District 6
    Current Status: The Contract Scope of Work has been sent to the Design Engineer for consideration (as of 02/12/2016 )

    Contracts (1) Progress
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/03/2015
    Project Initiation Form PIF Entered 02/02/2016
    Project Initiation Form PRC Submitted 02/02/2016
    Project Review Committee PRC Approved 02/11/2016
    Project Management
    Consultant Contract Process Scope to DE 02/12/2016