GREENFIELD- BRIDGE REPLACEMENT, G-12-006, NASH'S MILL ROAD OVER GREEN RIVER
This project will replace the existing Nash's Mill Road bridge over the Green River. The bridge will be reconstructed with wider shoulders and new sidewalks.
Location:
  • Town of Greenfield
  • Construction Begins: Summer 2018
    Resident Engineer: David Virgilio
    Construction Bid Price: $2,590,815.00
    District: District 2

    Contracts (1) Progress
    # 103655 -- Construction Contract
    Bridge Replacement Br. No. G-12-006 (Steel) Nash’s Mill Road over the Green River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/06/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/05/2015
    Project Initiation Form PIF Entered 06/10/2015
    Project Initiation Form PRC Submitted 06/12/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 04/07/2018
    Project Management
    100% Design 100% Package Received 11/27/2017
    100% Design 100% Package Comments to DE 01/09/2018
    25% Design 25% Package Received 05/31/2016
    25% Design 25% Package Received 02/17/2017
    25% Design 25% Package Comments to DE 04/11/2017
    25% Design 25% Package Approved 05/26/2017
    25% Design Design Public Hearing 05/25/2017
    75% Design 75% Package Received 07/24/2017
    75% Design 75% Package Comments to DE 09/25/2017
    Final Design PS&E Received 02/12/2018
    Final Design PS&E to FAPRO 03/28/2018