Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NORTHAMPTON- RECONSTRUCTION OF DAMON ROAD, FROM ROUTE 9 TO ROUTE 5, INCLUDES DRAINAGE SYSTEM REPAIRS & SLOPE STABILIZATION AT THE NORWOTTUCK RAIL TRAIL
The project consists of safety and transportation improvements along 1.1 miles of Damon Road, between Route 9 and Routes 5 &10 intersections in Northampton. The proposed drainage repairs consist of removing old headwalls, pipes and manholes, excavation of debris, construction of new drainage swale, and restoration of eroded bank west of Norwottuck Rail Trail in the area; and stabilization of the Connecticut River southern bank at the Trail bridge location.
Location:
  • City of Northampton
  • Construction Begins: Summer 2020
    Resident Engineer: Chunxia Feng
    Construction Bid Price: $9,496,858.00
    District: District 2

    Contracts (3) Progress
    # 111305 -- Construction Contract
    Roadway Reconstruction and Related Work(Including Signals) on Sections of Route 5 and Damon Road 100% Complete
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/03/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/05/2015
    Project Initiation Form PIF Entered 06/05/2015
    Project Initiation Form PRC Submitted 06/05/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 05/09/2020
    Project Management
    100% Design 100% Package Received 05/22/2018
    100% Design 100% Package Comments to DE 08/06/2018
    25% Design 25% Package Received 08/05/2016
    25% Design 25% Package Comments to DE 11/15/2016
    25% Design Design Public Hearing 05/09/2017
    75% Design 75% Package Received 09/18/2017
    75% Design 75% Package Comments to DE 01/18/2018
    Final Design PS&E Received 01/08/2019
    Final Design PS&E Received - Resub 1 02/04/2020
    Final Design PS&E Received - Resub 2 03/12/2020