Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WORCESTER- BOYLSTON- NORTHBOROUGH- STRUCTURAL STEEL CLEANING AND PAINTING AND VARIOUS REPAIRS OF OVERHEAD BRIDGES ON I-290
This project will consist of cleaning and painting of the structural steel (full clean and paint) superstructures for four overhead bridges over Interstate 290 in Worcester, Boylston and Northborough. The project will be funded with federal funds that are allotted for systematic bridge maintenance. The allotment (the district share) is $1,755,000.00 in FY2019.
Location:
  • Town of Boylston
  • Town of Northborough
  • City of Worcester
  • Construction Begins: Spring 2020
    Resident Engineer: Steven Crain
    Construction Bid Price: $1,942,500.00
    District: District 3

    Contracts (1) Progress
    # 109909 -- Construction Contract
    Structural Steel Cleaning, Painting and Repairs on 3 Bridges over Interstate 290 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/20/2020
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/08/2015
    Project Initiation Form PIF Entered 06/08/2015
    Project Initiation Form PRC Submitted 06/08/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 10/12/2019
    Project Management
    Final Design PS&E Received 08/07/2019
    Final Design PS&E Received - Resub 1 09/06/2019
    Final Design PS&E Received - Resub 2 09/18/2019