BOSTON- CALLAHAN TUNNEL CEILING RECONSTRUCTION, NEW JET FANS, AND OTHER CONTROL SYSTEMS
This project involves the removal of the existing Callahan Tunnel ceiling system and repair and fireproof tunnel, install jet fans and improve control system
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Hema P Bhatt
    Estimated Total Contract Cost: $20,125,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 115780 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/10/2015
    Project Initiation Form PIF Entered 06/10/2015
    Project Initiation Form PRC Submitted 06/10/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Management