Project Description:
MIDDLEFIELD- BRIDGE SUPERSTRUCTURE REPLACEMENT, M-19-010, CHESTER ROAD OVER SMART BROOK
Work consists of replacing the existing bridge structure.
Location:
  • Town of Middlefield
  • Construction Begins: Summer 2019
    Resident Engineer: Justin Bourbeau
    Construction Bid Price: $944,205.00
    District: District 1

    Contracts (2) Progress
    # 107203 -- Construction Contract
    Bridge Superstructure Replacement and Related Work Br. No. M-19-010 (Prefabricated Bridge Units) Chester Road over Smart Brook Completed
    # 77853 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 07/18/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/10/2015
    Project Initiation Form PIF Entered 06/10/2015
    Project Initiation Form PRC Submitted 06/10/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 03/09/2019
    Project Management
    100% Design 100% Package Received 10/01/2018
    100% Design 100% Package Comments to DE 11/01/2018
    100% Design 100% Plans Approved 11/29/2018
    25% Design 25% Package Received 10/20/2017
    25% Design 25% Package Comments to DE 11/20/2017
    25% Design 25% Package Received - Resub 1 11/02/2017
    25% Design Design Public Hearing 03/01/2018
    75% Design 75% Package Received 06/05/2018
    75% Design 75% Package Comments to DE 07/06/2018
    Final Design PS&E Received 12/21/2018
    Final Design PS&E to FAPRO 02/04/2019