Project Description:
ROYALSTON- BRIDGE REPLACEMENT, R-12-001 (B35), STOCKWELL ROAD OVER LAWRENCE BROOK
The original 1939/1985 structure was demolished in 2014. After its demolition, the bridge substructure was found to be supported directly at approximately bottom of the channel (mud line) level without footing. Existing abutment could not be utilized as temporary earth support for water control purpose.
Location:
  • Town of Royalston
  • Construction Begins: Spring 2018
    Resident Engineer: Matthew Minihan
    Construction Bid Price: $1,314,661.00
    District: District 2

    Contracts (2) Progress
    # 102193 -- Construction Contract
    Bridge Replacement Br. No. R-12-001 (Pre-Stressed Concrete Deck Beams) Stockwell Road over Lawrence Brook. Completed
    # 77872 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 06/21/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/10/2015
    Project Initiation Form PIF Entered 06/10/2015
    Project Initiation Form PRC Submitted 06/10/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 09/09/2017
    Project Management
    100% Design 100% Package Received 06/16/2017
    25% Design 25% Package Received 04/01/2016
    25% Design 25% Package Comments to DE 07/29/2016
    25% Design Design Public Hearing 10/27/2016
    75% Design 75% Package Received 01/09/2017
    Final Design PS&E Received 08/08/2017
    Final Design PS&E to FAPRO 08/22/2017
    Final Design PS&E Received - Resub 1 02/16/2018