Project Description:
BOSTON- SIDEWALK REPAIR & RELATED WORK AT STATE TRANSPORTATION BUILDING
The Scope of Work will include the design of replacement concrete sidewalks, wheelchair ramps, driveway reconstruction, resetting or replacement of granite curb where necessary and adjusting, resetting or replacing other sidewalk appurtenances as necessary and will include necessary improvements to accommodate pedestrians. All design elements of the project will meet current AAB/ADA standards, rules and regulations.
Location:
  • City of Boston
  • Construction Begins: Autumn 2016
    Resident Engineer: Patrick Finn
    Construction Bid Price: $836,828.00
    District: District 6

    Contracts (4) Progress
    # 115793 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77882 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 96338 -- Construction Contract
    State Transportation Building Sidewalk Repairs and Improvements along Charles, Stuart and Tremont Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/17/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/15/2015
    Project Initiation Form PIF Entered 06/15/2015
    Project Initiation Form PRC Submitted 06/15/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 07/23/2016
    Project Management
    100% Design 100% Package Received 04/12/2016
    100% Design 100% Package Comments to DE 05/10/2016
    100% Design 100% Plans Approved 05/10/2016
    100% Design 100% Plans Complete 05/10/2016
    25% Design 25% Package Received 01/15/2016
    25% Design 25% Package Comments to DE 02/22/2016
    25% Design 25% Package Approved 03/22/2016
    25% Design 25% Plans Complete 03/22/2016
    75% Design 75% Package Received 04/12/2016
    75% Design 75% Package Comments to DE 05/10/2016
    75% Design 75% Plans Approved 05/10/2016
    75% Design 75% Plans Complete 05/10/2016
    Final Design PS&E Received 06/28/2016
    Final Design PS&E to Peer Reviewer 06/30/2016
    Final Design Peer Review Comments to DE 07/07/2016
    Final Design PS&E to FAPRO 07/18/2016
    Consultant Contract Process Scope to DE 08/20/2015
    Consultant Contract Process NTP Issued 10/28/2015
    Consultant Contract Process Workhours Approved 09/25/2015