YARMOUTH- CORRIDOR IMPROVEMENTS ON ROUTE 28
The project consists of corridor improvements on Route 28 in Yarmouth, as well as upgrading the sidewalks, wheelchair ramps and driveway aprons to current AAB/ADA regulations and providing bicycle accommodations throughout the corridor. The project limits run from the Barnstable Town line to the Parkers River for a distance of approximately 2.5 miles.
Location:
  • Town of Yarmouth
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Thomas H Currier
    Estimated Total Contract Cost: $18,992,612.52
    Estimated Total Federal Participating Construction Cost: $21,603,481.87
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Cape Cod Metropolitan Planning Organization.
    District: District 5
    Current Status: Design Public Hearing (as of 11/21/2023 )

    Contracts (1) Progress
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: YARMOUTH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • RSA completed; CMAQ analysis to be completed; Project to be AC 2028-2029; TFPC $25,060,039; HSIP - $5,000,000 and STBG - $10,472,242
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $4,500,000.00
    State Cost: $500,000.00
    Total Cost: $5,000,000.00

    Planned Federal FY: 2028
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: YARMOUTH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • RSA completed; CMAQ analysis to be completed; Project to be AC 2028-2029; TFPC $25,060,039; HSIP - $5,000,000 and STBG - $10,472,242
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $8,377,793.60
    State Cost: $2,094,448.40
    Total Cost: $10,472,242.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/19/2015
    Project Initiation Form PIF Entered 06/19/2015
    Project Initiation Form PRC Submitted 06/19/2015
    Project Review Committee PRC Approved 01/31/2020
    Project Management
    25% Design 25% Package Received 03/03/2021
    25% Design 25% Package Comments to DE 09/13/2021
    25% Design 25% Package Approved 10/12/2023
    25% Design 25% Package Received - Resub 1 08/22/2022
    25% Design Design Public Hearing 11/21/2023
    25% Design 25% Plans Complete 10/12/2023
    Consultant Contract Process NTP Issued 09/26/2018