Project Description:
PEMBROKE- RESURFACING AND RELATED WORK ON ROUTE 53
Work on this project consists of mill and overlay on Route 53, drainage upgrades, sidewalk reconstruction, pavement markings and signs.
Location:
  • Town of Pembroke
  • Construction Begins: Summer 2020
    Resident Engineer: Russell Davis
    Construction Bid Price: $3,181,747.96
    District: District 5

    Contracts (2) Progress
    # 110284 -- Construction Contract
    Resurfacing and Related Work (Including Signals) on Sections of Route 53 (Washington Street) Completed
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/07/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/19/2015
    Project Initiation Form PIF Entered 06/17/2023
    Project Initiation Form PRC Submitted 06/19/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 11/30/2019
    Project Management
    100% Design 100% Package Received 09/05/2018
    100% Design 100% Package Comments to DE 01/23/2019
    75% Design 75% Package Received 07/18/2017
    75% Design 75% Package Comments to DE 01/29/2018
    Final Design PS&E Received 09/12/2019
    Final Design PS&E to FAPRO 11/18/2019