Project Description:
RAYNHAM- RESURFACING AND RELATED WORK ON ROUTE 138
Work on this project consists of mill and overlay on Route 138 from King Philip Street to Robinson Street. Also included in the project are drainage upgrades, sidewalk reconstruction, pavement markings and signs. Intersections will be reviewed for improvement per roadway safety audit recommendations.
Location:
  • Town of Raynham
  • Construction Begins: Autumn 2021
    Resident Engineer: James Sousa
    Construction Bid Price: $17,646,357.00
    District: District 5
    Current Status: Winter shutdown - wo work scheduled. Normal work hours are Monday thru Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 04/04/2024)

    Contracts (2) Progress
    # 115641 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on Sections of Route 138 (Broadway) 39% Complete
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/29/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Winter shutdown - wo work scheduled. Normal work hours are Monday thru Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/19/2015
    Project Initiation Form PIF Entered 06/19/2015
    Project Initiation Form PRC Submitted 06/19/2015
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 07/31/2021
    Project Management
    100% Design 100% Package Received 07/30/2020
    100% Design 100% Package Comments to DE 10/06/2020
    25% Design 25% Package Received 08/27/2018
    25% Design 25% Package Received - Resub 1 06/11/2019
    25% Design 25% Package Received - Resub 2 10/01/2019
    25% Design Design Public Hearing 08/27/2019
    75% Design 75% Package Received 12/18/2019
    75% Design 75% Package Comments to DE 02/18/2020
    Final Design PS&E Received 03/01/2021
    Final Design PS&E Received - Resub 1 06/07/2021