Project Description:
MALDEN- EXCHANGE STREET DOWNTOWN IMPROVEMENT PROJECT
The project will replace street lighting along Exchange Street from Abbott Street to just east of Middlesex Street. The project will provide new LED street lights to improve access and amenities in the Downtown Malden Business District. Sidewalks and ramps will be reconstructed in the area.
Location:
  • City of Malden
  • Construction Begins: Spring 2020
    Resident Engineer: Dylan Boyle
    Construction Bid Price: $1,947,150.62
    District: District 4
    Current Status: Project at full beneficial use, a few minor punch list items left to complete. (as of 11/14/2023)

    Contracts (1) Progress
    # 109995 -- Construction Contract
    Resurfacing and Related Work (Including ADA Improvements) on a Section of Exchange Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/08/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project at full beneficial use, a few minor punch list items left to complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/04/2015
    Project Initiation Form PIF Entered 08/04/2015
    Project Initiation Form PRC Submitted 09/01/2015
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 10/26/2019
    Project Management
    100% Design 100% Package Received 02/07/2019
    100% Design 100% Package Comments to DE 03/14/2019
    25% Design 25% Package Received 04/30/2018
    25% Design 25% Package Comments to DE 09/19/2018
    25% Design Design Public Hearing 10/25/2018
    75% Design 75% Package Received 02/06/2019
    Final Design PS&E Received 05/15/2019
    Final Design PS&E Received - Resub 1 09/05/2019