Project Description:
STOUGHTON- INTERSECTION IMPROVEMENTS AND RELATED WORK AT CENTRAL STREET, CANTON STREET AND TOSCA DRIVE
Work on this project consists of the installation of a traffic signal system and associated minor geometry. Improvements to mutli-modal accommodation, signs and pavement markings are also proposed. This project is proposed in conjunction with local initiatives advanced by the Town of Stoughton in the general vicinity.
Location:
  • Town of Stoughton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2023
    Project Manager: Shahpar Negah
    Estimated Total Contract Cost: $3,443,676.53
    Estimated Total Federal Participating Construction Cost: $4,419,675.82
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: 100% Package Comments to DE (as of 03/24/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: STOUGHTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Project Cost = $3,799,916 w/ $2,660,030 of STBG funding, and $1,139,886 of CMAQ funding,; d) MPO score 43.22
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,039,932.80
    State Cost: $759,983.20
    Total Cost: $3,799,916.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/14/2015
    Project Initiation Form PIF Entered 08/03/2016
    Project Initiation Form PRC Submitted 09/14/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Management
    100% Design 100% Package Received 12/23/2020
    100% Design 100% Package Comments to DE 03/24/2021
    25% Design 25% Package Received 06/29/2018
    25% Design 25% Package Comments to DE 11/08/2018
    25% Design Design Public Hearing 10/09/2019
    75% Design 75% Package Received 03/10/2020
    75% Design 75% Package Comments to DE 06/10/2020
    Consultant Contract Process NTP Issued 01/30/2017