Project Description:
STOUGHTON- INTERSECTION IMPROVEMENTS AND RELATED WORK AT CENTRAL STREET, CANTON STREET AND TOSCA DRIVE
Work on this project consists of the installation of a traffic signal system and associated minor geometry. Improvements to mutli-modal accommodation, signs and pavement markings are also proposed. This project is proposed in conjunction with local initiatives advanced by the Town of Stoughton in the general vicinity.
Location:
  • Town of Stoughton
  • Construction Begins: Autumn 2023
    Resident Engineer: Fedner Pierre
    Construction Bid Price: $3,900,192.25
    District: District 5
    Current Status: Forming and Pouring Concrete Sidewalks and Driveways. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 11/19/2024)

    Contracts (1) Progress
    # 123871 -- Construction Contract
    Intersection Improvements and Related Work at Central Street, Canton Street and Tosca Drive 52% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/11/2023
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Forming and Pouring Concrete Sidewalks and Driveways. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/14/2015
    Project Initiation Form PIF Entered 08/03/2016
    Project Initiation Form PRC Submitted 09/14/2016
    Project Review Committee PRC Approved 10/06/2016
    Project Status Advertised 08/26/2023
    Project Management
    100% Design 100% Package Received 12/23/2020
    100% Design 100% Package Comments to DE 03/24/2021
    25% Design 25% Package Received 06/29/2018
    25% Design 25% Package Comments to DE 11/08/2018
    25% Design Design Public Hearing 10/09/2019
    75% Design 75% Package Received 03/10/2020
    75% Design 75% Package Comments to DE 06/10/2020
    Final Design PS&E Received 01/27/2023
    Final Design PS&E Received - Resub 1 04/10/2023
    Final Design PS&E Received - Resub 2 07/20/2023
    Consultant Contract Process NTP Issued 01/30/2017