Project Description:
WEST SPRINGFIELD- ADAPTIVE SIGNAL CONTROL ON ROUTE 5 (RIVERDALE STREET)
Installation of adaptive traffic control signal equipment, vehicle detection, communication equipment, and managing software at 7 traffic signals (5 intersections + 2 pedestrian signals) on U.S. 5 in West Springfield
Location:
  • Town of West Springfield
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Jessica Gaudet
    Construction Bid Price: $384,564.00
    District: District 2

    Contracts (1) Progress
    # 96617 -- Construction Contract
    Installation of Adaptive Signal Control System at 7 Intersections along a Section of Route 5 (Riverdale Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/01/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/17/2015
    Project Initiation Form PIF Entered 08/17/2015
    Project Initiation Form PRC Submitted 10/26/2015
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 07/30/2016
    Project Management
    75% Design 75% Package Received 05/17/2016
    Final Design PS&E Received 06/24/2016
    Final Design PS&E to Peer Reviewer 06/24/2016
    Final Design PS&E to FAPRO 07/22/2016