FRAMINGHAM- NATICK- ADAPTIVE SIGNAL CONTROL ON ROUTE 9 (WORCESTER ROAD)
Installation of adaptive traffic control signal equipment, vehicle detection, communication equipment, and managing software at 5 traffic signals (3 in Framingham + 2 in Natick) on Route 9.
Location:
  • Town of Framingham
  • Town of Natick
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Alan Webb
    Construction Bid Price: $414,414.00
    District: District 3

    Contracts (1) Progress
    # 97251 -- Construction Contract
    Installation of Adaptive Signal Control System at 5 Intersections along a Section of Route 9 (Worcester Road and Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/30/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/17/2015
    Project Initiation Form PIF Entered 08/17/2015
    Project Initiation Form PRC Submitted 10/26/2015
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 08/20/2016
    Project Management
    100% Design 100% Package Received 07/15/2016
    100% Design 100% Package Comments to DE 08/02/2016
    25% Design 25% Package Received 06/08/2016
    25% Design 25% Package Comments to DE 07/01/2016
    75% Design 75% Package Received 06/08/2016
    Final Design PS&E Received 08/10/2016
    Final Design PS&E to FAPRO 08/12/2016