Project Description:
TEWKSBURY- RESURFACING AND SIDEWALK RECONSTRUCTION ON ROUTE 38 BEGINNING AT COLONIAL DRIVE NORTH TO THE INTERSECTION OF OLD BOSTON ROAD APPROXIMATELY 1.5 MILES
The scope of work for this project includes roadway resurfacing, sidewalk construction, and construction of ADA compliant access ramps. The limits are from the intersection of Colonial Drive north to the intersection of Old Boston Road for a distance of 1.5 miles.
Location:
  • Town of Tewksbury
  • Construction Begins: Autumn 2021
    Resident Engineer: Michael Pavao
    Construction Bid Price: $4,681,009.90
    District: District 4
    Current Status: All Contract work is complete. (as of 11/23/2023)

    Contracts (1) Progress
    # 116288 -- Construction Contract
    Resurfacing and Related Work on a Section of Main Street (Route 38) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/10/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    All Contract work is complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Received 09/23/2015
    Project Need Form PNF Entered 09/04/2015
    Project Initiation Form PIF Received 09/23/2015
    Project Initiation Form PIF Entered 09/23/2015
    Project Initiation Form PRC Submitted 09/23/2015
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 09/11/2021
    Project Management
    100% Design 100% Package Received 05/14/2021
    25% Design 25% Package Received 07/08/2020
    75% Design 75% Package Received 07/08/2020
    75% Design 75% Package Comments to DE 08/24/2020
    Final Design PS&E Received 05/14/2021
    Final Design PS&E Received - Resub 1 08/03/2021