Project Description:
|
BUCKLAND- BRIDGE MAINTENANCE, B-28-003, ROUTE 112 OVER ROUTE 2 AND PAN AM RAILROAD
Work to be done under this federal aid bridge maintenance contract includes replacement of the existing deck overlay (latex-modified concrete) and joint replacement. The bridge was originally built in 1997. The deck overlay replacement and joint replacements will include pre-compressed impregnated foam joint sealant, hydro-excavation of the deck overlay, and concrete work on both the approach slab and two feet of each deck end.
|