Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BRIMFIELD- WARREN- WEST SPRINGFIELD- WESTFIELD- STRUCTURAL REPAIRS ON FOUR BRIDGES ON I-90
The work to be done under this Contract consists of preparing structural repair designs and furnishing various artisans (iron workers, mechanics, welders, carpenters, laborers, operators, masons) and materials, supplies, equipment and engineering services to perform non routine structural maintenance and emergency repairs to various structures in District Two.
Location:
  • Town of Brimfield
  • Town of Warren
  • Town of West Springfield
  • City of Westfield
  • Construction Begins: Winter 2021/2022
    Resident Engineer: Matthew Fuller
    Construction Bid Price: $6,657,469.75
    District: District 2

    Contracts (1) Progress
    # 117036 -- Construction Contract
    Structural Repairs and Related Work (Including Painting) on 4 Bridges along Interstate 90 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/18/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/28/2015
    Project Initiation Form PIF Entered 10/01/2015
    Project Initiation Form PRC Submitted 10/01/2015
    Project Review Committee PRC Approved 10/07/2015
    Project Status Advertised 12/25/2021
    Project Management
    100% Design 100% Package Received 05/20/2021
    100% Design 100% Package Comments to DE 06/24/2021
    Final Design PS&E Received 08/27/2021
    Final Design PS&E Received - Resub 1 09/17/2021
    Final Design PS&E Received - Resub 2 11/04/2021
    Final Design PS&E Received - Resub 3 12/15/2021