Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
GRAFTON- CLEANING AND PAINTING 2 BRIDGES ON SNOW ROAD AND BRIGHAM HILL ROAD OVER I-90
This is a routine maintenance project that will address the cleaning and painting of two bridges in Grafton (Snow Road and Brigham Hill Road over I 90)
Location:
  • Town of Grafton
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Alyson Bedard
    Estimated Total Contract Cost: $884,450.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/29/2015
    Project Initiation Form PIF Entered 09/29/2015
    Project Initiation Form PIF Entered 09/29/2015
    Project Initiation Form PRC Submitted 09/29/2015
    Project Review Committee PRC Approved 10/07/2015
    Project Management