Project Description: |
CHARLTON- BRIDGE REHABILIATION, C-06-040, NORTHSIDE ROAD OVER I-90
This project will address the existing deterioration in deck, superstructure and substructure of this bridge.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Autumn 2028 |
Project Manager: | Caitlin A Marshall |
Estimated Total Contract Cost: | $3,866,182.00 |
Estimated Total Federal Participating Construction Cost: | $4,157,000.20 |
Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization. |
District: | District 3 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 11/02/2022 ) |
|
Bridges
|
|
|
|