Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SOUTHBOROUGH- WESTBOROUGH- BRIDGE REHABILITATION OF S-20-022, S-20-024 & W-24-032 & REPLACEMENT OF S-20-023
Location:
  • Town of Southborough
  • Town of Westborough
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2020
    Project Manager: Gary Baxter
    Estimated Total Contract Cost: $60,064,271.20
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 02/29/2020 )

    Contracts (3) Progress
    # 115753 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77850 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80651 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/29/2015
    Project Initiation Form PIF Entered 09/29/2015
    Project Initiation Form PRC Submitted 09/29/2015
    Project Review Committee PRC Approved 10/07/2015
    Project Status Advertised 02/29/2020
    Project Management
    25% Design 25% Package Received 12/23/2019
    25% Design 25% Package Comments to DE 01/13/2020
    25% Design 25% Package Approved 02/14/2020
    25% Design 25% Package Received - Resub 1 01/24/2020
    25% Design 25% Package Received - Resub 2 02/07/2020
    25% Design Design Public Hearing 02/27/2020
    Final Design PS&E to FAPRO 02/21/2020