Project Description:
CHELMSFORD- INTERSECTION IMPROVEMENTS AT ROUTE 129 AND RIVERNECK ROAD
The project will reconstruction Route 129 from Golden Cove Road to Industrial Avenue including rehabilitating the roadway surface, widening to include two 5 foot bike lanes and adding sidewalks on both sides. The intersection at Billerica Road will be realigned to form a T intersection. A rapid flashing beacon will be installed at the crosswalk near Industrial Avenue. Retaining walls will be installed to minimize impacts at River Meadow Brook and at the cemetery. A box culvert will be installed at the River Meadow Brook crossing of Billerica Road which will include a wildlife crossing. New drainage and stormwater detention will be included in the design.
Location:
  • Town of Chelmsford
  • Construction Begins: Autumn 2019
    Resident Engineer: Vincent DeAngelo
    Construction Bid Price: $5,938,848.00
    District: District 4

    Contracts (1) Progress
    # 108244 -- Construction Contract
    Intersection Improvements and Related Work Including Replacement of Bridge No. C-08-006 Route 129 (Billerica Road) at Riverneck Road Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/31/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/05/2015
    Project Initiation Form PIF Entered 10/05/2015
    Project Initiation Form PRC Submitted 10/05/2015
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 06/22/2019
    Project Management
    100% Design 100% Package Received 10/01/2018
    100% Design 100% Package Comments to DE 11/02/2018
    25% Design 25% Package Received 07/17/2017
    25% Design 25% Package Comments to DE 11/30/2017
    25% Design Design Public Hearing 06/28/2018
    75% Design 75% Package Received 10/01/2018
    75% Design 75% Package Comments to DE 11/02/2018
    Final Design PS&E Received 03/15/2019
    Final Design PS&E Received - Resub 1 05/17/2019