BEVERLY- INTERSECTION IMPROVEMENTS @ 3 LOCATIONS: CABOT STREET (ROUTE 1A/97) @ DODGE STREET (ROUTE 1A), COUNTY WAY, LONGMEADOW ROAD & SCOTT STREET, MCKAY STREET @ BALCH STREET & VETERANS MEMORIAL BRIDGE (ROUTE 1A) AT RANTOUL, CABOT, WATER & FRONT STREETS
The project involves updating and modernizing traffic signal equipment at the intersections of Cabot Street at Dodge Street/County Way/Longmeadow Road and Cabot Street at Rantoul Street/Front Street/Water Street/Goat Hill Lane; signalizing or installing a modern roundabout at the intersection of McKay Street at Balch Street; and proving on-street bicycle accommodations and ADA compliant wheelchair ramps at sidewalks at each intersection. Pavement milling and overlay at each intersection is also included in this work.
Location:
  • City of Beverly
  • Construction Begins: Spring 2020
    Resident Engineer: Michael Cannata
    Construction Bid Price: $6,268,275.00
    District: District 4

    Contracts (1) Progress
    # 110501 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at 3 Locations Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/26/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/13/2015
    Project Initiation Form PIF Entered 10/13/2015
    Project Initiation Form PRC Submitted 10/13/2015
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 12/28/2019
    Project Management
    100% Design 100% Package Received 09/03/2019
    100% Design 100% Package Comments to DE 10/16/2019
    25% Design 25% Package Received 06/06/2017
    25% Design 25% Package Comments to DE 10/13/2017
    25% Design Design Public Hearing 07/17/2018
    75% Design 75% Package Received 04/16/2019
    75% Design 75% Package Comments to DE 05/23/2019
    Final Design PS&E Received 11/20/2019
    Final Design PS&E to FAPRO 12/16/2019