DRACUT- IMPROVEMENTS ON NASHUA ROAD
The project involves reconstruction and widening of Nashua Road for improved vehicular, bicycle and pedestrian safety. Major intersection improvements are needed at Lakeview Avenue, Tyngsboro Road and Varnum Road to address obsolete geometry, lane configurations and capacity. Sidewalks are needed along the road to provide a safe area for pedestrians to walk. Shoulders are needed for errant vehicles and bicycle accommodation. A traffic signal is also needed at the NashuaRoad/Lakeview Avenue intersection to improve capacity and safety.
Location:
  • Town of Dracut
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2022
    Project Manager: Filbert Yee
    Estimated Total Contract Cost: $6,756,102.50
    Estimated Total Federal Participating Construction Cost: $7,660,795.85
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization.
    District: District 4
    Current Status: PS&E Received - Resub 1 (as of 07/21/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: DRACUT
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • N/A
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $225,527.20
    State Cost: $56,381.80
    Total Cost: $281,909.00

    Planned Federal FY: 2022
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: DRACUT
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • N/A
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,109,521.60
    State Cost: $1,027,380.40
    Total Cost: $5,136,902.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/15/2015
    Project Initiation Form PIF Entered 10/15/2015
    Project Initiation Form PRC Submitted 10/15/2015
    Project Review Committee PRC Approved 02/11/2016
    Project Management
    100% Design 100% Package Received 02/16/2021
    100% Design 100% Package Received 05/24/2021
    100% Design 100% Package Comments to DE 03/29/2021
    25% Design 25% Package Received 02/11/2019
    25% Design Design Public Hearing 01/16/2020
    75% Design 75% Package Received 08/03/2020
    75% Design 75% Package Comments to DE 10/20/2020
    Final Design PS&E Received 05/24/2021
    Final Design PS&E Received - Resub 1 07/21/2021