Project Description:
ADAMS- CHESHIRE- LANESBOROUGH- RESURFACING ON THE ASHUWILLTICOOK RAIL TRAIL, FROM THE PITTSFIELD T.L. TO THE ADAMS VISITOR CENTER
The existing 11.2 mile Ashuwillticook Rail Trail runs from the Pittsfield/Lanesborough line to the Adams Visitor Center and was constructed in two phases; completed in 2001 and 2004, respectively. As with other rail trails across the Commonwealth, over time the surface has begun to deteriorate; and root damage can cause serious public safety issues. The rail trail is currently at the stage where it requires reconstruction and resurfacing. Addressing these needs now will prolong service life of the trail, decrease the rate of further deterioration, and prevent more costly repairs in the future.
Location:
  • Town of Adams
  • Town of Cheshire
  • Town of Lanesborough
  • Construction Begins: Autumn 2019
    Resident Engineer: John Tietgens
    Construction Bid Price: $3,241,235.60
    District: District 1

    Contracts (1) Progress
    # 108457 -- Construction Contract
    Resurfacing and Related Work on the Ashuwillticook Rail Trai Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/12/2019
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/16/2015
    Project Initiation Form PIF Entered 10/16/2015
    Project Initiation Form PRC Submitted 10/16/2015
    Project Review Committee PRC Approved 02/16/2016
    Project Status Advertised 06/29/2019
    Project Management
    100% Design 100% Package Received 05/02/2019
    25% Design 25% Package Received 01/18/2019
    75% Design 75% Package Received 01/18/2019
    75% Design 75% Package Comments to DE 03/15/2019
    Final Design PS&E Received 05/02/2019
    Final Design PS&E to FAPRO 06/17/2019