Project Description:
SALEM- CANAL STREET RAIL TRAIL CONSTRUCTION (PHASE 2)
The project will construct 0.6 miles of shared off road path closing the gap between the existing Marblehead Rail Trail and the shared use path constructed along side Canal Street to Mill Street. The path will be 10 feet wide with 2 foot shoulders. The project includes the relocation of a railroad spur.
Location:
  • City of Salem
  • Construction Begins: Spring 2019
    Resident Engineer: Aldo Cassano Jr.
    Construction Bid Price: $3,039,796.00
    District: District 4
    Current Status: Project is 100% physically complete. (as of 01/02/2024)

    Contracts (1) Progress
    # 105924 -- Construction Contract
    Construction of Phase 2 of the Canal Street Rail Trail Shared Use Path from Canal to Roslyn Streets Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/14/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is 100% physically complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/16/2015
    Project Initiation Form PIF Entered 10/16/2015
    Project Initiation Form PRC Submitted 10/16/2015
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 09/15/2018
    Project Management
    100% Design 100% Package Received 06/08/2018
    25% Design 25% Package Received 03/16/2016
    25% Design Design Public Hearing 05/24/2017
    75% Design 75% Package Received 04/05/2017
    75% Design 75% Package Comments to DE 12/22/2017
    75% Design 75% Package Rejected 04/12/2017
    75% Design 75% Package Received - Resub 1 10/06/2017
    Final Design PS&E Received 08/14/2018
    Final Design PS&E to FAPRO 08/31/2018