Project Description:
WEST SPRINGFIELD- RECONSTRUCTION OF MEMORIAL AVENUE (ROUTE 147), FROM COLONY ROAD TO THE MEMORIAL AVENUE ROTARY (1.4 MILES)
The proposed Complete Streets roadway design will consist of milling and overlaying the existing roadway surface. The current concept consists of a road diet from a four lane traveled way to a two lane traveled way with a center two-way left turn lane. Other considerations are bike lanes, sidewalk reconstruction, updated signals, redesigned pedestrian crossings, and updated ADA accommodations.
Location:
  • Town of West Springfield
  • Construction Begins: Autumn 2022
    Resident Engineer: Andrew Grden
    Construction Bid Price: $27,002,392.00
    District: District 2

    Contracts (1) Progress
    # 118481 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) on a Section of Memorial Avenue (Route 147) 20% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/13/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/21/2015
    Project Initiation Form PIF Entered 02/22/2017
    Project Initiation Form PRC Submitted 02/24/2017
    Project Review Committee PRC Approved 03/23/2017
    Project Status Advertised 06/04/2022
    Project Management
    100% Design 100% Package Received 07/07/2021
    100% Design 100% Package Comments to DE 09/07/2021
    25% Design 25% Package Received 10/30/2017
    25% Design 25% Package Comments to DE 03/05/2018
    25% Design Design Public Hearing 04/30/2019
    75% Design 75% Package Received 07/02/2020
    75% Design 75% Package Comments to DE 09/30/2020
    Final Design PS&E Received 02/22/2022
    Final Design PS&E Received - Resub 1 04/04/2022
    Final Design PS&E Received - Resub 2 04/21/2022